How the estimate is built
A renovation budget is a list of line items. Some are measured, such as cabinetry by the lineal metre or tiling by the square metre; others are lump sums, such as a vanity or a plumber's quote. The estimator adds them up and puts a contingency on top.
Line cost = quantity × unit price, or the lump sum entered
Subtotal = Σ line costs Contingency = Subtotal × c ÷ 100 Total = Subtotal + Contingency
A lineal metre (lm) is a metre measured along the run of cabinets or benchtop, whatever its depth. c is the contingency percentage. For an extension the main line is floor area × build rate per m², plus the roof tie-in, approvals and design fees, and the result also shows the total per m² of new floor.
Worked examples with the default prices
The defaults are example prices for illustration, not market rates. Replace each one with a figure from your own quotes.
Kitchen. Cabinetry 4.5 lm × $1,500 = $6,750. Benchtop 4.5 lm × $700 = $3,150. Appliances $6,000. Splashback 3 m² × $300 = $900. Plumbing $2,500 and electrical $2,500. Flooring 12 m² × $100 = $1,200. Demolition $1,500. Labour 40 hours × $80 = $3,200. The subtotal is $27,700; a 10% contingency adds $2,770 for a total of $30,470.
Bathroom. Floor tiling 5 m² × $120 = $600 and wall tiling 20 m² × $120 = $2,400. Vanity $1,200, shower screen $900, toilet $500, waterproofing $1,500, plumbing $4,000, electrical $1,500, demolition $1,500 and labour 40 × $80 = $3,200. Subtotal $17,300, contingency $1,730, total $19,030.
Extension. 30 m² × $3,000 = $90,000, plus a roof tie-in of $8,000, approvals of $4,000 and design fees of $6,000: a subtotal of $108,000. The 10% contingency is $10,800 and the total $118,800, which is $118,800 ÷ 30 = $3,960 per m² of new floor.
Getting a useful number
Measure before you price. Lineal metres of cabinetry and benchtop, and the square metres of floor and wall to tile, drive most of a kitchen or bathroom budget. Measure wall tiling to the height you actually plan to tile, and deduct only large openings such as doors and windows.
Avoid counting labour twice. Many quotes are supply-and-install. If a tiler's price per m² already includes laying, or the cabinetmaker installs, keep the separate labour line for work nobody else has quoted, such as carpentry, patching or fit-off.
Contingency. Renovations uncover hidden problems: rotten framing, old wiring, uneven floors, failed waterproofing under the old tiles. A contingency is not a sign the budget is wrong; it is the allowance for what nobody can see before demolition. Older houses usually warrant a larger percentage than recent ones.
An extension is more than its floor area. Joining a new roof to the old, matching floor levels, moving services and upgrading the existing switchboard can all sit outside a builder's rate per m². Approval pathways and fees differ between councils, so ask your council or a certifier early.
Licensed trades
Plumbing, electrical and waterproofing work in Australia is regulated by each state and territory. In New South Wales, the NSW Government says a licence is needed for all specialist work, which includes electrical wiring, plumbing, drainage and gasfitting, regardless of its cost, and for residential building work valued at more than $5,000 including GST in labour and materials (NSW Government, “Checking your contractor or tradesperson is qualified”, checked 19 November 2026). For waterproofing, and for every other state and territory, check your state's licensing rules before you engage anyone or plan to do work yourself, and ask each trade for their licence number.