How the materials are counted
A retaining wall is priced on four things: the units that form the face, what holds them in place (a footing for blocks, posts set in concrete for sleepers), the drainage behind the wall, and labour. The calculator counts each from the wall length L and the height H showing above the ground in front, with all dimensions in metres.
Segmental blocks. Dry-stacked concrete blocks lock together with lips or pins and hold the soil by their weight.
Courses = ⌈H ÷ hb⌉ + cb Blocks per course = ⌈L ÷ wb⌉
hb is the block height, wb the face width and cb the number of courses buried below the ground in front. The ⌈ ⌉ brackets mean round up, because a part course or part block still has to be filled. Caps = ⌈L ÷ cap length⌉. The spare allowance is added to blocks and caps and the result rounded up again.
Sleepers and posts. Timber or concrete sleepers slide between steel H or C posts set in concrete.
Bays = ⌈L ÷ s⌉ Posts = bays + 1 Rows = ⌈H ÷ hs⌉ Sleepers = bays × rows
s is the sleeper length, which sets the post centres, and hs the sleeper height. Each post is the built height (rows × hs) plus the embedment, and each hole holds π × d² ÷ 4 × embedment of concrete, where d is the hole diameter. That ignores the small volume of the post itself, so it errs on the generous side.
Drainage aggregate V = L × Hw × b Ag pipe = L + outlet run Geotextile = L × (Hw + 2b) × (1 + overlap)
Hw is the built height of the wall, b the width of the drainage zone (300 mm is a common starting figure), and the aggregate tonnes are V times its loose density. The fabric is taken to line the back and bottom of the drainage zone and fold over the top, so the gravel does not clog with soil.
Worked example: a 6 m block wall 600 mm high
- Courses. With 400 × 200 mm blocks, 0.6 ÷ 0.2 = 3 courses show, plus 1 buried: 4 courses, built 0.8 m high.
- Blocks. 6 ÷ 0.4 = 15 blocks per course, 4 × 15 = 60 blocks. With 5% spare, 60 × 1.05 = 63.
- Caps. 15 caps of 400 mm, and 15 × 1.05 = 15.75, so 16 with spare.
- Strip footing. 6 × 0.5 × 0.15 = 0.45 m³ of concrete.
- Drainage. 6 × 0.8 × 0.3 = 1.44 m³, and at 1.6 t/m³ that is 2.304 tonnes.
- Pipe and fabric. 6 + 2 = 8 m of ag pipe. Fabric is 6 × (0.8 + 0.6) = 8.4 m², or 9.24 m² with 10% for overlaps.
- Cost at the example prices. 63 × $8 = $504, 16 × $10 = $160, 0.45 × $300 = $135, 2.304 × $80 = $184.32, 8 × $3 = $24 and 9.24 × $2 = $18.48. The subtotal is $1,025.80; 10% contingency adds $102.58 for $1,128.38.
A 7.2 m sleeper wall 800 mm high with 2.4 m × 200 mm sleepers has 3 bays and 4 posts, 4 rows and 12 sleepers, or 13 with 5% spare. With 900 mm embedment each post is 0.8 + 0.9 = 1.7 m long. A 450 mm hole 0.9 m deep holds 0.1431 m³, so four holes take 0.5726 m³. Drainage is 7.2 × 0.8 × 0.3 = 1.728 m³ (2.7648 t), the pipe 9.2 m and the fabric 11.088 m². At the example prices that is $1,267.73 before contingency and $1,394.50 with 10%.
Where the estimate stops
Engineering and approval. This is a quantity estimate, not a design. Walls above a certain height, or carrying loads such as a driveway, a building, a pool or a sloping bank above, need engineering design and may need council approval. The height that triggers this differs between councils and states, and a wall near a boundary or an easement can have its own rules, so check with your local council before you order anything. Follow the block or post maker's installation guide and the National Construction Code where it applies.
Water is the usual cause of failure. Most retaining walls that lean or fall do so because water builds up behind them. The aggregate, the pipe at the base and a clear outlet to a legal discharge point matter as much as the blocks. Do not backfill the drainage zone with clay or site soil.
Rounding and site conditions. Corners, steps in the base, curves and changes in height add blocks, cuts and posts that a straight-run count does not see. The last sleeper in a run usually has to be cut, and the last bay may be shorter than the others. Price stock post lengths, which may be longer than the length shown.
Prices are yours. Every price on the page is an example. Get quotes, and check whether a supplier charges aggregate by the tonne or by the cubic metre and whether delivery is extra.