How the pavers and layers are worked out
A paved area is built in layers: a compacted crushed rock base, a thin screeded bed of sand, the pavers, and fine sand brushed into the joints, all held in by an edge restraint. Each layer is worked out from the net area A, which is the length times the width (or the area you enter) less any cut-out that will not be paved.
Pavers = ⌈A × (1 + w) ÷ ((l + j) × (b + j))⌉
l and b are the paver length and width and j the joint width, all in metres, so each paver plus its share of joint covers (l + j) × (b + j). w is the waste allowance as a fraction: about 5% for straight or stretcher bond, and about 10% for herringbone or diagonal layouts, which need cuts along every edge. These are common starting figures, not rules. ⌈ ⌉ means round up. Pavers per m² is 1 ÷ ((l + j) × (b + j)).
Bedding sand = A × ds Base (loose) = A × db × k Tonnes = volume × ρ
ds is the bedding sand depth, db the finished (compacted) base depth, k the compaction factor that turns a compacted volume into the loose volume to order, and ρ the loose bulk density of each material. Jointing sand is A times a rate in kilograms per square metre, which depends on the paver size, joint width and depth: narrow joints between large pavers take much less than brick-sized pavers.
Worked example: a 5 m × 4 m patio
- Net area. 5 × 4 = 20 m², less a 1 m² garden bed, leaves 19 m².
- Paver module. A 400 × 400 mm paver with a 3 mm joint covers 0.403 × 0.403 = 0.162409 m², which is 6.157 pavers per m².
- Pavers. Straight lay with 5% waste: 19 × 1.05 = 19.95 m², and 19.95 ÷ 0.162409 = 122.84, so 123 pavers, with a face area of 123 × 0.16 = 19.68 m².
- Bedding sand. 19 × 0.03 = 0.57 m³, and at 1.6 t/m³ that is 0.912 tonnes.
- Base. 19 × 0.1 = 1.9 m³ compacted; × 1.2 = 2.28 m³ loose; at 1.5 t/m³, 3.42 tonnes.
- Jointing sand and edging. 19 × 2 = 38 kg of jointing sand, and a perimeter of 2 × (5 + 4) = 18 m of edge restraint.
- Cost at the example prices. 123 × $5 = $615, 0.912 × $60 = $54.72, 3.42 × $55 = $188.10, 38 × $1 = $38 and 18 × $15 = $270. The subtotal is $1,165.82; 10% contingency adds $116.58 for $1,282.40.
Ignoring the joint would give 19.95 ÷ 0.16 = 124.69, or 125 pavers, two more than needed. Joints matter far more with small pavers: 230 × 115 mm pavers with 3 mm joints come to 36.37 per m², and the same 19 m² laid herringbone with 10% waste needs 761 of them.
Getting the order right
Base beyond the edge. The base usually runs a little past the paved edge to support the edge restraint. If yours does, add that strip to the area for the base, or work the base separately in the gravel calculator.
Driveways. Paving that carries cars needs a deeper, well-compacted base and often thicker pavers laid in a pattern that interlocks. The 100 mm default is for foot traffic only. Take the depth from the paver maker's guide, or from an engineer where the subgrade is soft or the loads are heavy.
Compaction and density. The factor and densities are typical figures, not properties of any product. Ask your supplier what their crushed rock weighs per cubic metre, and whether they sell by the tonne or the cubic metre. If you enter a compacted density, set the factor to 1, or the weight will be overstated.
Buy from one batch. Colour can vary between production runs, so order the full quantity, spares included, at once and mix pavers from several pallets as you lay.
Prices are yours. Every price on the page is an example to replace with a quote. Delivery, hire of a plate compactor and saw, and removal of excavated soil are not included unless you add them to the labour line or the contingency.