CalcTrace

Concrete Calculator

Work out how much concrete a slab, footing, wall, rectangular or round column, beam or set of steps needs. Results are in cubic metres, or cubic yards if you switch to imperial, with a waste allowance and the number of premix bags for the yield printed on your bag.

Last updated .

What are you pouring?

Shape
Units
m
m
mm
%
L

This default is an example, not a figure for any product. Replace it with the yield printed on your bag. See how to read the yield.

Result

ConcreteBefore wasteTo order

This is a volume estimate only. Thickness, reinforcement and concrete strength are design decisions for your engineer, builder or local building rules.

Show the working

    The volume formulas

    Concrete is ordered by volume, so every job comes down to finding the volume of the shape being filled. The one rule that matters is to put every measurement into the same unit before multiplying. In metric that means metres, so a thickness given in millimetres is divided by 1,000 first.

    Slab, footing or wall: V = L × W × T

    L is the length, W the width and T the thickness, or the depth for a footing and the height for a wall. All three are in metres and V is in cubic metres.

    Rectangular column: V = W × D × H

    Rectangular beam: V = W × D × L

    For a column, W and D are the two sides of its cross-section and H its height. For a beam, W is the width, D the depth and L the length between supports, or the full length if it runs continuously over them.

    Round column: V = π × (D ÷ 2)² × H

    D is the diameter and H the height, both in metres. π is about 3.1416. Half the diameter is the radius, and the radius squared times π is the area of the circular end.

    Solid steps: V = W × R × G × n × (n + 1) ÷ 2

    W is the width of the flight, R the rise of one step, G the going (the depth of one tread from front to back) and n the number of steps. The formula treats the flight as a stack of blocks: the first step is one rise tall, the second two rises, and so on, each one going deep. Four steps therefore contain 1 + 2 + 3 + 4 = 10 blocks. Stairs cast with a sloping underside use less than this.

    Volume to order = V × number of items × (1 + waste % ÷ 100)

    Premix bags = volume to order ÷ yield of one bag, rounded up

    Worked example: a 5 m by 3 m slab

    A shed slab is 5 m long, 3 m wide and 100 mm thick, with a 10% waste allowance.

    1. Convert the thickness. 100 mm ÷ 1,000 = 0.1 m.
    2. Multiply. 5 × 3 × 0.1 = 1.5 cubic metres.
    3. Add the waste. 1.5 × 1.10 = 1.65 cubic metres to order.
    4. Bags, if mixing by hand. 1.65 cubic metres is 1,650 litres. With the example yield of 9 litres a bag, 1,650 ÷ 9 = 183.3, so 184 bags.

    The other default shapes work the same way. A strip footing 10 m long, 300 mm wide and 400 mm deep is 10 × 0.3 × 0.4 = 1.2 cubic metres. A rectangular column 300 mm by 400 mm and 3 m high is 0.3 × 0.4 × 3 = 0.36 cubic metres, and a beam 300 mm wide, 500 mm deep and 6 m long is 0.3 × 0.5 × 6 = 0.9 cubic metres. A round column 300 mm across and 2.4 m high is 3.1416 × 0.15² × 2.4 = 0.17 cubic metres. Four steps 1.2 m wide with a 175 mm rise and a 280 mm going are 1.2 × 0.175 × 0.28 × 10 = 0.588 cubic metres.

    Imperial units

    In imperial mode, lengths are entered in feet and thicknesses in inches, and inches are divided by 12 to get feet. A slab 10 ft by 10 ft and 4 in thick is 10 × 10 × 0.3333 = 33.33 cubic feet. There are 27 cubic feet in a cubic yard, so that is 1.23 cubic yards. One cubic yard is 0.7646 cubic metres.

    How to read the yield on a premix bag

    The yield is the volume of mixed concrete one bag makes, and it depends on the product and the bag size, so this calculator does not assume one. Look on the back of the bag or the product data sheet for one of two statements.

    The yield assumes the amount of water stated on the bag. Adding more water does not make more usable concrete; it weakens it.

    Getting the estimate right

    Mixing units is the usual error. Multiplying 5 × 3 × 100 without converting the thickness gives 1,500, a thousand times too much. If a result looks absurd, check the millimetres.

    Measure the thickness you will actually pour. Ground that has been dug by hand is never flat. Check the depth at several points and use the average, or the deepest figure if you want a margin. An extra 10 mm across the slab above adds 5 × 3 × 0.01 = 0.15 cubic metres, the same as the whole 10% allowance.

    Choose the waste allowance to suit the job. Many builders add between 5% and 10% for spillage and uneven formwork: on 1.5 cubic metres, 5% gives 1.575 and 10% gives 1.65. Footings poured straight into a rough trench can need more, because the trench is always wider than drawn.

    Think about the bag count before committing to hand mixing. The 184 bags in the example, if they were 20 kg bags, weigh 3,680 kg before water is added. Premix suits posts, small pads and repairs. For anything larger, ask a ready-mix supplier for a price, tell them the volume to order, and ask how they round it, because plants deliver in fixed increments.

    Beams cast with a slab. Where a beam is poured together with the slab above it, the top of the beam is already part of the slab volume. Enter only the depth below the slab: a 500 mm beam under a 150 mm slab adds 0.3 × 0.35 × 6 = 0.63 cubic metres, not 0.9.

    Irregular shapes. Split an L-shaped slab into two rectangles, calculate each and add them. Use “How many of these” for repeated items such as a row of identical post holes.