How the bars and the mass are worked out
A round steel bar is a long cylinder, so its mass per metre is its cross-sectional area times the density of steel. The calculator uses 7,850 kg/m³, the nominal density of steel used in bar tables.
Area of one bar A = π × d² ÷ 4 (mm²)
Mass per metre m = 7,850 × π × d² ÷ 4 (kg/m, with d in metres)
Here d is the nominal bar diameter. Because 7,850 × π ÷ 4,000,000 is very close to 1 ÷ 162, site crews often use the rule of thumb m ≈ d² ÷ 162 with d in millimetres. It always comes out 0.12% high, which is harmless for ordering.
The number of bars across a distance follows from the space left once the cover is taken off both sides:
n = ⌊(W − 2c) ÷ s⌋ + 1
Bar length = run length − 2c
W is the distance the bars are spread across, c the end and edge cover, s the centre-to-centre spacing, and ⌊ ⌋ means round down. The extra 1 is the fencepost: four gaps need five bars. With one-way bars, the bars run along the length and are counted across the width. A two-way mesh adds a second set running along the width, counted across the length. Total length is the bar count times the bar length for each direction, then the allowance is added and the result multiplied by the mass per metre.
Steel area per metre width As = (1,000 ÷ s) × π × d² ÷ 4 (mm²/m)
Mass and area of each bar size
| Diameter | Area (mm²) | Mass (kg/m) | d² ÷ 162 |
|---|---|---|---|
| 6 mm | 28.3 | 0.222 | 0.222 |
| 8 mm | 50.3 | 0.395 | 0.395 |
| 10 mm | 78.5 | 0.617 | 0.617 |
| 12 mm | 113.1 | 0.888 | 0.889 |
| 16 mm | 201.1 | 1.578 | 1.580 |
| 20 mm | 314.2 | 2.466 | 2.469 |
| 24 mm | 452.4 | 3.551 | 3.556 |
| 25 mm | 490.9 | 3.853 | 3.858 |
| 28 mm | 615.8 | 4.834 | 4.840 |
| 32 mm | 804.2 | 6.313 | 6.321 |
| 36 mm | 1,017.9 | 7.990 | 8.000 |
| 40 mm | 1,256.6 | 9.865 | 9.877 |
Worked example: a 6 m × 4 m two-way mesh of 12 mm bars
A slab 6 m long and 4 m wide gets 12 mm bars at 200 mm centres both ways, with 50 mm cover at every edge and a 10% allowance for laps and waste.
- Mass per metre. π × 0.012² ÷ 4 = 0.00011310 m², and × 7,850 = 0.8878 kg/m. The rule of thumb gives 144 ÷ 162 = 0.8889 kg/m.
- Bars along the length. Space across the width: 4,000 − 2 × 50 = 3,900 mm. 3,900 ÷ 200 = 19.5, round down to 19, add 1: 20 bars. Each is 6 − 0.1 = 5.9 m long, so 20 × 5.9 = 118 m.
- Bars along the width. Space across the length: 6,000 − 100 = 5,900 mm. 5,900 ÷ 200 = 29.5, so 29 + 1 = 30 bars, each 4 − 0.1 = 3.9 m: 30 × 3.9 = 117 m.
- Totals. 20 + 30 = 50 bars and 118 + 117 = 235 m. With the allowance, 235 × 1.10 = 258.5 m.
- Mass. 258.5 × 0.8878 = 229.5 kg, or 0.2295 tonnes. Without the allowance it is 208.6 kg.
- Steel area. 1,000 ÷ 200 = 5 bars per metre, × 113.1 mm² = 565.5 mm²/m in each direction.
The 20 bars span 19 × 200 = 3,800 mm, which leaves 100 mm of the 3,900 mm unused, and the 30 bars span 5,800 of 5,900 mm. Split that between the two edges, or the outer bars sit 100 mm further from one edge than the cover.
Reading the result
Spacing is centre to centre. Drawings give the distance between bar centres, not the clear gap. If the spacing is a maximum, as it usually is, and the leftover space matters, add one bar per direction and close the spacing up slightly.
Cover is concrete outside the steel. Cover protects the bar from corrosion and fire, so the required figure depends on exposure and is set by the designer. This page takes it off both ends of every bar and both edges of every layer.
Laps add real length. Bars longer than the stock length you can buy, and bars that join onto starter bars, overlap by a lap length that can be many bar diameters. The percentage allowance is a rough cover for laps, offcuts and waste. For a closer figure, work out the laps and add them, using the rebar development length calculator.
Use a bar schedule for the real order. A schedule lists every bar mark with its shape, cut length and count, including bends, hooks, chairs and top steel. This calculator gives straight bars in one layer, which is the right figure for an estimate and a check on a schedule.
Supplier masses differ slightly. Manufacturers' tables use the nominal diameter, but some round the mass or quote a value for a deformed bar's actual profile. Expect differences of a percent or so, and use the supplier's figure when you pay by the tonne.