How the boards and framing are worked out
Drywall, called plasterboard in Australia, is bought by the sheet, so the estimate starts from the area to be lined. Walls are measured as the perimeter times the height, the doors and windows come off, and the ceiling is added if it is being boarded too.
Board area A = (P × h − openings) × faces + ceiling area
P is the total length of wall in metres, h the ceiling height and faces the number of wall faces or layers boarded: 1 for lining the inside of a room, 2 for a partition lined both sides or a wall with two layers of board. For a rectangular room P = 2(L + W) and the ceiling is L × W.
Boards = ⌈A × (1 + waste ÷ 100) ÷ board area⌉
A 1200 × 2400 mm board covers 2.88 m², a 1200 × 2700 mm board 3.24 m², and a 4 × 8 ft board exactly 32 ft², which is 2.9729 m² because a foot is defined as 0.3048 m.
Studs per wall run = ⌊run length ÷ spacing⌋ + 1
One stud stands at each spacing mark along the wall plus one at the end. The four walls of a rectangular room are counted as four runs, so each corner gets a stud from each wall. Openings need extra studs either side and cripple pieces above and below, and corners often need another for backing, so add those in the extra studs box.
Track (top and bottom plate) = 2 × P Screws = boards × screws per board
Compound = A × kg per m² Tape ≈ A ÷ board width
The tape formula treats the lined area as strips one board wide, so every board contributes about one long edge joint. It is approximate: butt joints at board ends add tape, and the outside edges of the room need none.
Worked example: a 4 × 3.5 m room, walls and ceiling
- Walls. The perimeter is 2 × (4 + 3.5) = 15 m. At 2.4 m high that is 36 m², less 3 m² for a door and window, 33 m².
- Ceiling. 4 × 3.5 = 14 m², so the board area is 33 + 14 = 47 m².
- Boards. With 10% waste, 47 × 1.1 = 51.7 m², and 51.7 ÷ 2.88 = 17.95, so 18 boards of 1200 × 2400 mm. With 1200 × 2700 mm boards it is 15.96, so 16 boards; with 4 × 8 ft boards 17.39, so 18.
- Studs at 600 mm. Each 4 m wall: 4 ÷ 0.6 = 6.67, so 6 + 1 = 7 studs. Each 3.5 m wall: 3.5 ÷ 0.6 = 5.83, so 5 + 1 = 6. Two of each make 26 studs. At 400 mm centres it is 11 and 9 studs per wall, 40 in all.
- Track. 2 × 15 = 30 m of top and bottom track or plate.
- Screws. 18 × 32 = 576 screws.
- Compound. 47 × 0.5 = 23.5 kg at the example rate.
- Tape. 47 ÷ 1.2 = 39.17 m, about 39 m.
If the same room were a partition lined on both sides of every wall, the wall area doubles to 66 m² and the board area becomes 80 m², 30.56 boards of 2.88 m² with waste, so 31 boards and about 67 m of tape. The studs and track do not change, because both faces fix to the same frame.
Reading the result and common mistakes
Waste depends on the layout. Ten per cent suits a plain room. Rooms with many openings, raking ceilings or short walls cut more boards and may need 15% or more. Choosing a board length that matches the wall height cuts the waste and the butt joints: a 2.7 m board on a 2.7 m wall has no end joint at all.
Openings are not free. Subtracting the full door and window area is correct for boards but generous for compound and tape, because every opening adds corner bead and cut edges to finish.
Screw counts vary. The fixing pattern depends on the board, the frame spacing, whether adhesive is used and whether the board is on a wall or ceiling. Thirty-two is a typical planning figure, not a requirement; follow the board maker's fixing guide.
Compound rate. Joint compound use depends on the product, the number of coats and the finish level wanted. The 0.5 kg/m² default is an example to replace with the figure on your product's data sheet.
Framing size and spacing. This page counts studs; it does not check whether a stud size can span the wall height or carry a load. Wall height limits, bracing and load-bearing walls are matters for the frame supplier's tables, an engineer or your local building rules.